5.3.3
Navigational dredging
(including capital projects)
a. Extent
of the activity
Dredging is a fundamental
requirement for most harbours and ports
[124] . Within this
section dredging can be defined as, the
excavation of material from the seabed
and the relocation of the excavated material
elsewhere for disposal. In general, dredging
may be undertaken for a variety of purposes
including navigation, flood control and
for beach nourishment purposes. In Ceredigion,
dredging is carried out to improve navigation
and falls into two categories:
Maintenance Dredging:
Maintenance dredging
is the routine / periodic removal of material
in approach channels and basins to assist
safe access for vessels. This may vary
from an almost continuous activity throughout
the year to an infrequent activity occurring
only once every few years. Generally, for
the purpose of a disposal licence, if a
period of 10 years has lapsed between a
new and previous dredge, the operation
will be treated as capital dredging where
disposal at sea is involved.
Capital Dredging:
Capital dredging is the
excavation of sediments for the first time
so as to increase water depths in an area
to accommodate vessels (excavation therefore
generally takes place in virgin material).
Arising from disposal licensing requirements,
capital dredging also includes the removal
of material from previously dredged areas
where sedimentation has since occurred
and has not been disturbed by further dredging
over a period of time (10 years or greater).
i. Within
the site
Maintenance dredging
requirements at New Quay and Aberaeron
harbours are as follows:
New Quay: Some
3000 tonnes of sand are removed annually
from the main harbour and Penpolion and
is deposited at Dolau for beach replenishment
purposes. These operations are carried
out at low tide, using shore plant.
Aberaeron: Material
is removed from the harbour at intervals
of approximately 4 years and has been used
for sea defence. There is a need to dredge
the inner Harbour (Pwll Cam). Previous
dredging activity has been temporarily
suspended because the methods used (tipping
over the sill for the tide to carry away)
were no longer acceptable to Environment
Agency Wales. Any new scheme would be likely
to fall within the capital dredging category
in view of the timescales involved (see
above).
ii. Adjacent
to the site
Aberystwyth: The
dredging of the harbour channel is carried
out every 2 years whilst the inner harbour
(including the marina) is dredged approximately
every 4 years. Selected suitable dredged
material has been used to replenish South
Beach, Aberystwyth.
Cardigan: Limitations
on navigation within the Teifi estuary
have given rise to concern amongst boat
users. Levels on the bar are similar to
those of 60 yrs ago, but the channel moves
around. Proper marking of the channel could
limit the need for dredging. There is no
dredging regime currently in place and
the County Council has previously commissioned
consultants to investigate options for
capital and maintenance dredging within
the estuary to improve navigation. This
issue is to be considered as part of the
process of preparing a Teifi Estuary Management
Plan (to be published in June 2000), also
taking account of the high conservation
value of the estuary.
Fishguard & Milford
Haven: Dredging is not known to have
taken place in Fishguard Harbour for
some time, though it is presumed there
will be the occasional requirement for
it. Significant dredging is required
occasionally from Milford Haven waterway.
Several studies to select an alternative
spoil dumping ground have taken place
since the early 1990s when concerns
were raised about increased sedimentation
within the Skomer Marine Nature Reserve.
b. Mechanism
for effect on the feature
The potential impacts
of dredging upon the bottlenose dolphin
and its habitat are two-fold: firstly as
a result of the dredging itself and secondly
as a result of the disposal of the dredged
material. These impacts can relate to activities
both within and adjacent to the SAC.
i. Habitat
impacts
Direct impacts are typically
in the form of removal or smothering of
benthic habitats and communities. Loss
of fine fractions during dredging and disposal
operations (if at sea) results in settlement
of fines on the sea bed, possibly some
distance from the site of the operation.
This distance depends on local hydrology
and particle size. Removal (dredging) or
accretion (disposal) of sediments may,
in the long-term, affect the sediment regime
locally and possibly at some distance.
Impacts on the dolphins habitat may
affect abundance and distribution of dolphin
prey. See Prey
Depletion.
ii. Noise
Vessel based navigational
dredging is noisy and involves the use
of several vessels on a standard back
and forth route. Effects are likely
to be negligible when using shore plant,
as is currently the case at New Quay. See Noise.
iii. Pollution
Pollutants bound within
the dredged sediments may be remobilised
either in solution or bound to fines. Pollutants
may also be released from the dredger and
associated shipping. These may become biologically
available, be assimilated, and enter the
food chain. Certain substances subject
to bioaccumulation and biomagnification
would be of greatest threat to top predators
such as the bottlenose dolphin. See Pollution.
iv. Collisions
Increased shipping movements
will result in an increased potential for
collisions between vessels and with dolphins.
See Shipping and Collisions.
c. Management
Response
i. Rationale
Harbour activity within
and adjacent to the SAC is centred on New
Quay, Aberaeron and Aberystwyth. These
harbours are mainly used by fishing vessels
and recreational craft. The County Council,
as the Harbour Authority for Ceredigion,
has responsibility for navigation in these
harbours and their dredging is generally
required to maintain navigable depths.
Mooring facilities are
also available in the Teifi estuary where
local concern has been expressed that navigation
is becoming progressively restricted through
the silting of the estuary.
In addition to the Habitats
Regulations, the following legislation
can have a bearing on proposals for dredging
and disposal:
-
Coast Protection
Act 1949;
-
Deposits in
the Sea (exemptions) Order 1985;
-
Environment
Act 1995;
-
Environmental
Protection Act 1990;
-
Food and Environment
Protection Act (Part 2) 1985 (FEPA);
-
Harbour Act
1964
-
Harbour Works
(Assessment of Environmental Effects)
Regulations 1988;
-
Harbour Works
(Assessment of Environmental Effects)
(Amendment) 1996;
-
Landfill Tax
Regulations 1996;
-
Waste Management
Licensing Regulations 1994;
-
Town and Country
Planning Act 1990;
-
Various
local harbour powers
Consents
issued for navigational dredging may, therefore,
be numerous and be required from several
competent authorities. Most commonly within
the Bay, consents are issued by CCC (Harbour
Act 1964), NAW (Food and Environment Protection
Act (Part 2) 1985 (FEPA)) but undertaken
by MAFF on their behalf, DETR (Coast Protection
Act 1949).
There is a requirement
under the Habitats Regulations to review
existing consents, and any new dredging
developments would certainly constitute
plans and projects and be subject to the
significance/appropriate assessment procedure
for the purposes of the Habitats Directive
(see Figure
17.). Competent authorities should
therefore ensure that the potential impacts
on the bottlenose dolphins and their habitat
are fully addressed in such assessments.
Almost
all potential effects of dredging and dumping
on the bottlenose dolphins are secondary
in nature. Due to the small nature of dredging
events in Cardigan Bay harbours it is unlikely
that any one dredging operation, if properly
managed, would be large enough to have
a significant impact in its own right.
Proper avoidance of sensitive areas and
proper analysis of sediment composition
prior to choosing the most appropriate
disposal methods would probably mitigate
the potential for such single event impacts.
However, dredging events are typically
recurrent and whilst possibly not significant
in their own individual right may, cumulatively,
have the potential for long term impact
on the dolphins either directly or through
their habitat and food.
ii. Type
of Response
F1 :
The activity constitutes a plan
or project.
iii. Actions,
including links to other policies/plans/measures
Actions
- Treat all navigational
dredging as a plan or project.
- Review extant
maintenance dredging operations and
produce Dredging Plans to provide a
framework/procedure for proposals for
dredging within Ceredigion.
- Use the best
practicable environmental option for
the disposal of dredged material.
- Establish a
code of practice for dredging and disposal
in and adjacent to the SAC.
Links: Other
coastal management plans
- Ensure that
any proposals for navigational dredging
are assessed in the context of the
relevant Shoreline Management Plan.
- The possibility
of improving dredging in the Teifi
estuary to improve navigation will
be explored within the Teifi Estuary
Management Plan.
- Ensure the
Teifi Estuary Management Plan is consistent
with the SAC Management Plan.
[124]
Further information on interactions between
Port & Harbour operations and features
of UK marine SACs can be found in: ABP
Research. 1999. Good practice guidelines
for ports and harbours operating within
or near UK European marine sites. English
Nature, UK Marine SACs Project. pp120. This
report is available with other related
information at: http://www.english-nature.org.uk/uk-marine/ |